There was quite a bit of progress this week on the plumbing. That will all be finished up in a couple of days, and then the electric will start. The weather didn’t cooperate for the tree trimmers, but the views were still better than they’ve been with the wind having cleared most of the leaves off of the trees.
The upstairs bathroom has a shower/tub. The downstairs bath will have a tiled shower, so it’s just pipes now.
The washer connections are also in place on the first floor.
Outside, the ac unit has been put in place. AC was the last thing we were thinking about as it was 32 degrees. It won’t get a whole lot colder than that here, so for November 1st, it’s a bit nippy.
One of the two windows that’s yet to be installed is the window for the closet turned office nook. This will be a small window similar in size to the one in the bathroom below it. You can see it framed out in the picture.
I forgot to get a picture of the front door last week, so here it is.
The outside won’t change now for a couple of weeks. The roof will go on in 3-4 weeks, and the framing crew will be back in a week or two to start on the exterior. Everything in the meantime will happen inside.

The porch is still the highlight for me. If you don’t like this porch, you’re just not a porch person.